The project life-cycle can be described as ( ).
A、project concept, project planning, project execution, and project close-out
B、project planning, work authorization, and project reporting
C、project planning, project control, project definition, WBS development, and project termination
D、project concept, project execution, and project reporting
項目生命周期劃分正確的是( )。
A、啟動、計劃、執(zhí)行、收尾
B、計劃、授權(quán)、報告
C、計劃、控制、方案設計、WBS的發(fā)展、終止
D、啟動、執(zhí)行、報告
A project life cycle is a collection of generally sequential project ( ) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (-) for managing the project, regardless of the specific work involved.
A、phases
B、processes
C、segments
D、pieces
一個項目的生命周期由若干個順序相連的( )組成,階段的名字和個數(shù)由組織的控制需要決定,項目涉及到的其他組織,其控制需要也可決定項目階段的名字和個數(shù)。無論涉及到的具體的工作有哪些,項目的生命周期都為管理項目提供了基本的(-)。
A、階段
B、過程
C、片段
D、碎片
A project life cycle is a collection of generally sequential project (-) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ( ) for managing the project, regardless of the specific work involved.
A、plan
B、fraction
C、main
D、framework
一個項目的生命周期由若干個順序相連的(-)組成,階段的名字和個數(shù)由組織的控制需要決定,項目涉及到的其他組織,其控制需要也可決定項目階段的名字和個數(shù)。無論涉及到的具體的工作有哪些,項目的生命周期都為管理項目提供了基本的( )。
A、計劃
B、部分
C、主體
D、框架
Estimating schedule activity costs involves developing an (-) of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives.for example,in mostapplication areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estmates are generally expressed in units of (-) to facilitate comparisons both within and across projects. the ( ) describes important information about prject requirement that is considered duing cost estimating.
A、project scope statement
B、statement of work
C、project management plan
D、project policy
估算計劃活動的成本涉及估算完成每項計劃活動所需資源的近似成本。成本估算包括識別和考慮各種成本計算方案。例如,在大多數(shù)的應用領(lǐng)域,普遍在設計階段多做些額外工作以降低執(zhí)行階段和產(chǎn)品運行時的潛在成本。成本估算過程考慮預期的成本節(jié)省是否能夠彌補額外設計工作的成本。成本估算一般以貨幣單位表示,以利于在項目內(nèi)和項目間進行比較。項目范圍說明書描述了項目的商業(yè)要求、理由、需求和當前邊界。它提供了關(guān)于在成本估算時必須考慮的項目需求的重要信息。
The ( ) technique involves using project characteristics in a mathematical model to predict total project cost.models can be simple or complex.
A、cost aggregation
B、reserve analysis
C、parametric estimating
D、funding limit reconciliarion
參數(shù)估算涉及在一個數(shù)學模型中利用項目特性來預測整體項目成本。模型可以是簡單的也可以是復雜的。
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |