系統(tǒng)集成項目管理工程師每日練習題(2024/3/28)
試題1
( )不屬于“識別風險”過程的輸入。試題2
work performance information is circulated through( ) processes.試題3
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
系統(tǒng)集成項目管理工程師每日練習題答案解析(2024/3/28)
試題1
信管網(wǎng)參考答案:A
信管網(wǎng)參考解析:識別風險的輸入: 1、風險管理計劃;2、成本管理計劃; 3、進度管理計劃;4、質量管理計劃;5、人力資源管理計劃;6、范圍基準;7、活動成本估算;8、活劫持續(xù)時間估算;9、干系人登記冊; 10、項目文件;11、采購文件; 12、事業(yè)環(huán)境因素;13、組織過程資產(chǎn)
識別風險的輸入:http://www.ichunya.com/pm1/57364.html
試題2
信管網(wǎng)參考答案:D
信管網(wǎng)參考解析:工作績效信息通過( )過程進行傳播。
A計劃 B變更 C改善 D溝通
試題3
信管網(wǎng)參考答案:B
信管網(wǎng)參考解析:
掙值分析技術是一種綜合了范圍、成本、進度指標的常用績效測量方法。它幫助項目團隊評價項目績效。如果一個項目的進度績效指數(shù)SPI值小于1,意味著()。
A.進度超前B.進度滯后 C成本超支 D成本結余
SPI值小于1表示實際進度落后于計劃進度。
因此,正確答案應選B。
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內容不斷變化與調整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |