深夜成人在线,chinese国产一区二区,欧美精品乱码,日韩欧美在线视频免费观看,国产午夜不卡,日韩av影院在线,五月天婷婷国产精品

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project budget is proving to be inaccurate. The SPI is 1.1, the team has had negative deviation from the activity attributes, and the sponsor has inserted herself on the change control board. What is the best thing for the project manager to do ?
A、Try to encourage the sponsor to remove herself from the change control boad.
B、 Re-compute the project schedule.
C、 Re-estimate the activity attributes.
D、 Calculate the cost performance index.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容