深夜成人在线,chinese国产一区二区,欧美精品乱码,日韩欧美在线视频免费观看,国产午夜不卡,日韩av影院在线,五月天婷婷国产精品

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project is using a productive infrastructure in a large operating environment. The project is an accident occurred at this time, but a technical solution is implemented to resolve the problem. Despite the circumstances a project stakeholders are still complaints because:
A、The project sponsor had not received any notification, and without the approval of the chosen option.
B、 The risk was not identified and assessed, and update in the risk log.
C、 The change control board was informed, and the incident was not evaluated.
D、 The change created a risk that could have caused a major operational impact.


相關(guān)試題

推薦文章