深夜成人在线,chinese国产一区二区,欧美精品乱码,日韩欧美在线视频免费观看,国产午夜不卡,日韩av影院在线,五月天婷婷国产精品

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the project performance is reviewed, the project manager identifies some activities that cannot be completed on time, because of poor team performance. What would be next step ?
A、Offer rewards for team members willing to work overtime to meet project needs.
B、 Look for root causes that may be affecting team performance.
C、 Review the schedule to align it to current team performance.
D、 Promise training sessions to increase team performance.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容