試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

In a project which uses local resources, the organization made some necessary adjustments to the budget and goals, which led to reduction in duration of the project and cost of non-local resources. The project manager decides to increase resources and budget. Which of the following should the project manager take ?
A、Share.
B、 Enhance.
C、 Accept.
D、 Exploit.