It is predicted that a project’s early finish date is 1 March. The customer insists that the project manager provide an accurate late finish date with 99.99 level of confidence. What is the latest finish date the project manager will commit to, if the calculated schedule deviation is 4 days ?
A、March 5
B、March 25
C、April 1
D、April 25