深夜成人在线,chinese国产一区二区,欧美精品乱码,日韩欧美在线视频免费观看,国产午夜不卡,日韩av影院在线,五月天婷婷国产精品

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The project manager is briefing management on project status and identifies a negative schedule variance but a positive cost variance. Which of the following conclusion is reasonable?
A、The project is behind schedule but may be brought back on schedule by adding resource
B、The project is ahead of schedule but over budget and needs further investigation
C、The project is behind schedule, over budget and merits serious concern
D、The project is ahead of schedule, under budget and progressing with no obvious issues


相關試題

推薦文章