深夜成人在线,chinese国产一区二区,欧美精品乱码,日韩欧美在线视频免费观看,国产午夜不卡,日韩av影院在线,五月天婷婷国产精品

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager is leading the implementation of a solution that involves several emerging technologies. As a result, the project manager expects that the original project planning documents may need to be updated several times throughout the project life cycle to adjust overall project direction.What should the project manager do?
A、Develop detailed project organization charts and empower subject matter experts to approve any necessary technical scope change
B、Establish a direct and dynamic communication path with senior leadership so they are engaged in every change request
C、Inform the senior leadership that the project could not be developed once the risk of failure is identified
D、Design and implement an integrate change control system to report, control, and record changes to the original project baseline


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容