試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

During the project's construction phase, a supplier has a fire and the supply of raw material is delayed by a week, The project manager identified the risk of a delay and included it in the plan .After the occurrence of the event, what should the project manager do first?
A、Carry out risk response planning
B、Ask for an extension of the project due to delay
C、Update the project baseline
D、Update the risk register