深夜成人在线,chinese国产一区二区,欧美精品乱码,日韩欧美在线视频免费观看,国产午夜不卡,日韩av影院在线,五月天婷婷国产精品

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Due to external impacts,the project is canceled by the steering committee at an SPI of 0. 5. what should the project manager do next?
A、Perform an EVA to find whether the CV or the SV is the reason for the SPI of 0. 5
B、Proceed with closure process to transfer the project’s finished and unfinished deliverable to others
C、Nothing,when the project is officially closed by the steering committee, no closure processes required.
D、Conduct a root cause analysis to find the reasons for the cancellation of the project


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容