A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(  ).
A、assign change tasks to project members
B、call a meeting of the configuration control board
C、change the scope baseline
D、postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline