As a project nears completion, a stakeholder is replaced, the project team is busy completing development of the few remaining requirements, the project managers first meeting with the new stakeholders is next week, but the stakeholder has already sent several emails, asking for change to requirements that have already been implemented, what should the project manager do next?
在一個項目即將完成時,一位相關方被替換,項目團隊正在忙著完成剩余幾項需求的開發(fā),項目經理與新相關方的第一次會議安排在下周,但該相關方已經發(fā)送了幾封電子郵件,要求變更已經實施的要求,項目經理下一步應該怎么做?
A.Inform the new stakeholder that changes to requirements this later in the project will result in cost and schedule overruns通知該新相關方,在項目后期變更需求將導致成本和進度超支
B.Discuss the requested changes with the team and determine the impact of incorporating them into the final deliverables與團隊討論所請求的變更,并確定將其納入最終可交付成果的影響
C.Ask management to attend the meetings with the new stakeholder to discuss the issue要求管理層一起參加與該新相關方的會議,以討論該問題
D.Inform the new stakeholder that the requested changes cannot be implemented as they are not included in the approved scope通知該新相關方無法實施所請求的變更,因為它們未包含在已批準的范圍內
信管網參考答案:B
信管網解析:
B是參考答案。根據變更流程,分析討論實施的影響。C的問題在于變更審批的主要群體是CCB而不是管理層。參考講義變更處理流程。
信管網訂閱號
信管網視頻號
信管網抖音號
溫馨提示:因考試政策、內容不斷變化與調整,信管網網站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網軟考課程由信管網依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |