深夜成人在线,chinese国产一区二区,欧美精品乱码,日韩欧美在线视频免费观看,国产午夜不卡,日韩av影院在线,五月天婷婷国产精品

專業(yè)PMP?項目管理網(wǎng)站|服務(wù)平臺|服務(wù)商 (PMP?項目管理學(xué)習(xí)QQ群:975119573,客服QQ:800184589)

軟題庫 學(xué)習(xí)課程
當(dāng)前位置:信管網(wǎng) >> PMP? >> 每日一練 >> 文章內(nèi)容
PMP?每日一練試題(2022/7/6)

PMP?當(dāng)天每日一練試題地址:www.ichunya.com/exam/ExamDay.aspx?t1=33

往期PMP?每日一練試題匯總:www.ichunya.com/class/27/e33_1.html

PMP?每日一練試題(2022/7/6)在線測試:www.ichunya.com/exam/ExamDay.aspx?t1=33&day=2022/7/6

點(diǎn)擊查看:更多PMP?習(xí)題與指導(dǎo)

PMP?每日一練試題內(nèi)容(2022/7/6)

  • 試題1

    A project manager is verifying that all project-deliverable documents are updated and all issues are resolve What process does this decision
    項目經(jīng)理正在核實所有項目可交付成果文件已更新,且所有問題均已解決。這描述了什么過程
    A、Manage project knowledge. 管理項目知識。
    B、Close project or phase. 結(jié)束項目或階段。
    C、Monitor and control project work. 監(jiān)控項目工作。
    D、Perform integrated change control. 實施整體變更控制。

    查看答案

    試題參考答案:B

    試題解析與討論:www.ichunya.com/st/478719986.html

  • 試題2

    圖表中的每個數(shù)據(jù)點(diǎn)都代表一個項目的報告期,第一個數(shù)據(jù)點(diǎn)最接近于0。

    第八個報告期的項目狀態(tài)是?
    A、成本超支,進(jìn)度落后
    B、成本節(jié)約,進(jìn)度落后
    C、成本節(jié)約,進(jìn)度提前
    D、成本超支,進(jìn)度提前

    查看答案

    試題參考答案:B

    試題解析與討論:www.ichunya.com/st/4624211687.html

  • 試題3

    項目團(tuán)隊包括項目經(jīng)理共有15人,團(tuán)隊遇到意外問題,需額外增加團(tuán)隊資源,項目經(jīng)理額外獲取三名團(tuán)隊成員。為什么項目經(jīng)理了解項目溝通渠道的數(shù)量很重要?
    A、項目經(jīng)理必須了解該數(shù)量,以便決定是否采用正式或非正式溝通
    B、該數(shù)量與溝通的復(fù)雜性成反比
    C、項目經(jīng)理必須了解該數(shù)量,以便制定一份經(jīng)過批準(zhǔn)的溝通計劃
    D、溝通管理復(fù)雜性隨該數(shù)量的增多而增加

    查看答案

    試題參考答案:D

    試題解析與討論:www.ichunya.com/st/473593168.html

  • 試題4

    A project manager is assigned to a project to replace an outdated system. During installation the equipment is damaged and requires technical resources to repair it. What document must be updated to communicate this occurrence with the st keholders?
    項目經(jīng)理被任命管理一個取代過時系統(tǒng)的項目。在安裝過程中設(shè)備損壞,需要技術(shù)資源修理。必須更新什么文件來與相關(guān)方溝通這種情況?
    A、Issue log 問題日志
    B、Status report 狀態(tài)報告
    C、Incident management plan 事件管理計劃
    D、Resource allocation matrix 資源分配矩陣

    查看答案

    試題參考答案:A

    試題解析與討論:www.ichunya.com/st/48362861.html

  • 試題5

    在一個施工項目中,項目經(jīng)理希望外包現(xiàn)場邊界墻的建設(shè)。潛在供應(yīng)商受邀參加會議。采購公司的建筑設(shè)計師準(zhǔn)備了一份邊界墻的施工成本估算,但未與潛在供應(yīng)商分享。這屬于以下哪項技術(shù)?
    A、獨(dú)立估算
    B、建議書評價技術(shù)
    C、專家判斷
    D、篩選系統(tǒng)

    查看答案

    試題參考答案:A

    試題解析與討論:www.ichunya.com/st/4889825931.html

  • 試題6

    A customer has given you a procurement statement of work f or a complex,eight-month project that has a few unknowns.T he customer has asked you to just"get it done” and only wan ts to see you at the end of eight months when you deliver the finished project.Under these circumstance.which of the following is the BEST thing to do?
    一位客戶交給你一份采購工作說明書,要求你去完成一個復(fù)雜的、為期八個月的項目??蛻舾嬖V你,他只想在8 個月后項目結(jié)束時得到他想要的。不過,在接到SOW 后,你發(fā)現(xiàn)還有幾個要點(diǎn)尚未明確??蛻粢竽阒还苋プ鼍秃昧?,而且只希望在8個月后你把完成的項目交給他。在這種情況下,你比較合適的做法是∶
    A、Complete the project as requested,but verify its scope with the customer occasionally throughout. 開始項目,但是要不定期讓客戶核實范圍
    B、Complete the project within eight months without contacting the customer during this time. 開始項目,8個月后讓客戶核實范圍
    C、Ask management to check in with the customer occasionally. 讓管理層與客戶不定期接觸
    D、Complete the project,but document that the customer did not want contact. 開始項目,并將客戶不愿意中途聯(lián)絡(luò)的要求記錄下來

    查看答案

    試題參考答案:A

    試題解析與討論:www.ichunya.com/st/476191896.html

  • 試題7

    What should a project manager do when asked to complete a project's administrative closure earlier than expected 
    在被要求預(yù)期時間更早地完成項目的行政收尾時.項目經(jīng)理應(yīng)該做什么
    A、Re-baseline the requirements specifications. 重定需求規(guī)范的基準(zhǔn)。
    B、Ensure that project documentation is archive 確保項目文檔已存檔。
    C、Update the issue log. 更新問題日志。
    D、Submit a change request. 提交變更請求。

    查看答案

    試題參考答案:D

    試題解析與討論:www.ichunya.com/st/4783527119.html

  • 試題8

    The project team discovers that a critical activity is behind schedule. The project manager must identify when the project started to fall behind schedule. What should the project manager do next?
    項目團(tuán)隊發(fā)現(xiàn)關(guān)鍵活動落后于進(jìn)度。項目經(jīng)理必須確定項目何時開始落后于進(jìn)度。項目經(jīng)理接下來應(yīng)該怎么做?
    A、Revise the work breakdown structure to determine complex activities with long durations
    修改工作分解結(jié)構(gòu),確定持續(xù)時間長的復(fù)雜活動
    B、Revise activity duration estimates to identify the longest task before the critical activity
    修改活動持續(xù)時間估算,確定關(guān)鍵活動之前持續(xù)時間最長的任務(wù)
    C、Use expert judgment to recall identified issues within the project
    使用專家判斷,回憶項目中確定的問題
    D、Use the corresponding schedule baseline to determine delays
    使用相應(yīng)的進(jìn)度基準(zhǔn)來確定延誤

    查看答案

    試題參考答案:D

    試題解析與討論:www.ichunya.com/st/494818527.html

  • 試題9

    在執(zhí)行階段,客戶告訴項目經(jīng)理,三個現(xiàn)有工具的軟件版本已更改。現(xiàn)在,三個接口必須以不同方式實施。項目經(jīng)理應(yīng)該怎么做?
    A、更新工作分解結(jié)構(gòu)(WBS)
    B、更新風(fēng)險登記冊
    C、開始變更管理過程
    D、審查項目管理計劃

    查看答案

    試題參考答案:C

    試題解析與討論:www.ichunya.com/st/4711224486.html

  • 試題10

    Each time you meet with your project sponsor, she emphasizes the need for cost control on your new-business project. She always asks you about cost performance in terms of which budgets have been met and which have been met and which have not. To answer her concerns,you should provide. 
    每次你與你的項目發(fā)起人會面,她都要強(qiáng)調(diào)對于你的新的電子商務(wù)項目的成本控制的必要性。她經(jīng)常詢問你成本業(yè)績方面的問題,諸如哪一個預(yù)算達(dá)到了哪一個沒有達(dá)到。為了回答她的問題,你應(yīng)該提供()
    A、Cost Performance baseline 
    成本績效基準(zhǔn)
    B、Performance measurement graphs and charts 
    業(yè)績衡量圖表
    C、Resource productivity analyses
    資源生產(chǎn)力分析
    D、Trend analysis statistics 
    趨勢分析統(tǒng)計

    查看答案

    試題參考答案:A

    試題解析與討論:www.ichunya.com/st/48986553.html

信管網(wǎng)訂閱號

信管網(wǎng)視頻號

信管網(wǎng)抖音號

溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!

信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。

信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。

相關(guān)內(nèi)容

發(fā)表評論  查看完整評論  

報考條件查詢

推薦文章

精選

課程

提問

評論

收藏