信息系統(tǒng)項目管理師當天每日一練試題地址:www.ichunya.com/exam/ExamDay.aspx
往期信息系統(tǒng)項目管理師每日一練試題匯總:www.ichunya.com/class27-1-1.aspx
信息系統(tǒng)項目管理師每日一練試題(2018/7/23)在線測試:www.ichunya.com/exam/ExamDay.aspx?day=2018/7/23
信息系統(tǒng)項目管理師每日一練試題內容(2018/7/23)
試題1: Many of the activities performed during the preliminary investigation are still being conducted in(1 ), but in much greater depth than before. During this phase, the analyst must become fully aware of the(2 ) and must develop enough knowledge about the(3 ) and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4 ) for process and data of current system, the deliverable from this phase also includes the(5 ) for the proposed system.
(1)A. analysis phase
B. design phase
C. implementation phase
D. maintenance phase
(2)A. main symptom
B. root problem
C. final blueprint
D. data specification
(3)A. hardware environment
B. testing environment
C. software environment
D. business environment
(4)A. logical models
B. physical models
C. design models
D. implementation models
(5)A. hardware and software specification
B. system performance specification
C. formal requirements definition
D. general problem statement
在描述復雜關系時,圖形比文字敘述優(yōu)越得多,下列四種圖形工具中,不適合需求分析階段使用的是( )
A. 層次方框圖
B. 用例圖
C. IPO圖
D. N_S圖
甲乙兩個公司在項目實施過程中,對合同的生效時間產(chǎn)生了分歧。仲裁機構調查時發(fā)現(xiàn)以下事實:①雙方簽署的合同上并沒有對合同的生效日期做出規(guī)定;②雙方簽署合同的過程如下:乙公司在擬定好合同文本并簽署后以郵寄的方式寄給甲公司,信封上蓋有乙公司所在地郵局3月18日的郵戳,甲公司于3月20日收到合同文本,甲公司簽署合同后,將合同回寄給乙公司,信封帶有甲公司所在地3月22日的郵戳,乙公司于3月25日收到合同。仲裁機構應判定( )作為合同生效的日期。
A.3月18日 B.3月20日 C.3月22日 D.3月25日
某企業(yè)需要采用甲、乙、丙三種原材料生產(chǎn)Ⅰ、Ⅱ兩種產(chǎn)品。生產(chǎn)兩種產(chǎn)品所需原材料數(shù)量、單位產(chǎn)品可獲得利潤以及企業(yè)現(xiàn)有原材料數(shù)如表所示:
則公司可以獲得的最大利潤是(1)萬元。取得最大利潤時,原材料(2)尚有剩余。
(1)A.21 B.34 C.39 D.48
(2)A.甲 B.乙 C.丙 D.乙和丙
某政府部門擬利用中央財政資金建設電子政務項目,關于建設方的立項管理,下列做法中不符合有關規(guī)定的是( )。
A.建設單位在編制項目建議書時專門組織項目需求分析,形成需求分析報告,報送項目審批部門
B.建設方在項目建議書獲得批復后,招標選定有資格的第三方工程咨詢機構編制可行性研究報告,報送項目審批部門
C.建設方在可行性研究報告獲得批復后,向有關部門申請項目前期工作經(jīng)費,前期工作經(jīng)費計入項目總投資
D. 建設方在可行性研究報告獲得批復后,委托有資格的第三方工程咨詢機構出具評估意見,連同批復的項目建議書,作為項目建設的主要依據(jù)
A project life cycle is a collection of generally sequential project(1 )whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic (2 )for managing the project, regardless of the specific work involved.
(1)A. phases B. processes C. segments D. pieces
(2)A.plan B. fraction C. main D. framework
建立一個概率模型或者隨機過程,使它的參數(shù)等于問題的解,然后通過對模型或過程的觀察計算所求參數(shù)的統(tǒng)計特征,最后給出所求問題的近似值,解的精度可以用估計值的標準差表示。這種技術稱為( )方法
A 期望貨幣分析
B 決策樹分析
C 蒙特卡洛分析
D 優(yōu)先順序圖
質量保證是項目管理中非常重要的活動,質量保證除了為項目提供支持外,還為()創(chuàng)造了條件。
A、產(chǎn)品改進
B、過程改進
C、質量控制
D、成本控制
代理服務器防火墻主要使用代理技術來阻斷內部網(wǎng)絡和外部網(wǎng)絡之間的通信,達到隱蔽內部網(wǎng)絡的目的。以下關于代理服務器防火墻的敘述中,()是不正確的。
A.僅“可以信賴的”代理服務才允許通過
B.由于已經(jīng)設立代理,因此任何外部服務都可以訪問
C.允許內部主機使用代理服務器訪問Internet
D.不允許外部主機連接到內部安全網(wǎng)絡
溫馨提示:因考試政策、內容不斷變化與調整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,官方教材參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。